Project Management (Operations)
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
1) Question - This is anything that interferes with transmission and understating of massage
Ans: Noise
2) Question – Jargons need to be avoided.
Ans: TRUE
3) Question - Fixed cost define as expenses that are not directly dependent on the activities of the project.
Ans: TRUE
4) Question - Ans:
A) Version 1 - Oldest version running well at
B) Version 2- The customer typically goes
C) Version 3- Undergoing system testing at
D) Version 4- Half cooked status
5) Question – Initiation phase include activities such as project scope define
Ans: Project selection, Project development , Project design
6) Question - Internet banking is the example of ________ demand.
Ans: Business
7) Question - Ans:
A) In SMART technique the letter S means Specific
B) In SMART technique the letter M means Measurable
C) In SMART technique the letter A means Achievable
D) In SMART technique the letter R means Realistic
8) Question - Scope can be defined for project as well as project.
Ans: TRUE
9) Question - ______ is nothing but a list of all planned expenses.
Ans: - Budget
10) Question - Enterprise Resource planning (ERP) is a
Ans: Software tool
11) Question - It is the effort required to test a program to ensure that it performs its intended function
Ans: Testability
12) Question - Example of external risks are
Ans: delays caused by third party vendor, natural calamities
13) Question - Most of the project failures are attributed to weak project management.
Ans: TRUE
14) Question - Every project, physical or software with basic two types of characteristics
Ans: intrinsic, extrinsic
15) Question - The project managers should involve their team members in risk identification process.
Ans: TRUE
16) Question - ________ is a process of reaching to mutual agreement.
Ans: Negotiating.
17) Question - There is various problems solving technique available.
Ans: Cause-Effect Diagram, SWOT Analysis, Flow Charts
18) Question - Schedule is usually show in tabular or in a graphical chart called as
Ans: Gantt chart
19) Question -
Ans:
20) Question - Rational unified process has four phases some of these are
Ans: Elaboration, Transformation, inspection
21) Question - Constraints help in making schedule, budget and risk planning.
Ans: TRUE
22) Question - In real life to adjust the schedule, we need to consider which activities are really dependent and which activities can be executed parallel. This can be well understood by determining the
Ans: Type of dependency
23) Question - The principles in Lean manufacturing are
Ans: Eliminate waste, Amplify learning
24) Question - Slandered are basically
Ans: Audits
25) Question - Given the many weaknesses in the Indian financial system Indian entrepreneur who intended to start a software firm greatly benefited from
Ans: Natural recourses
26) Question - In the ________ approach, each team a responsible for completing some of the products.
Ans: Multidisciplinary
27) Question - Every organization operates in a ____________ environment.
Ans: Socio-economic
28) Question - This determines how early an activity can start
Ans: Early start